All Saints Square Kings Heath















Planning permission was recently granted for the re-location of the toilets, outside All Saints Church, to move to the opposite corner of Vicarage Road. The relocation of the toilets will allow work to commencing on the new community square outside All Saints Church. The plan is to relocate the toilets in late November early December.
The council owned highway land has been through a stopping up order procedure and will shortly pass to the church allowing the Community Spaces grant to be drawn down and work on the community square to begin.  commence. 
It is envisaged that a contractor for doing the works will be appointed in mid December, with them starting on site in mid January, with a completion  and formal opening of the square planned for July 2011.